Natick Director of Public Works John Westerling this week briefed the Select Board on the town’s pavement management plan, which depending on where you live in town, might be more or less exciting than it sounds (see presentation slides below or watch a recording from Pegasus starting at about the 34-minute mark).
The town has 128 miles of accepted roads (and another 26 miles of unaccepted ones… private ones, subdivision streets, etc., that the DPW isn’t responsible for maintaining). So the pavement management plan focuses on the accepted ones, but the unaccepted ones aren’t forgotten about—the town has a newish process through which people can request to have a street accepted and they should reach out to the Engineering Division to learn more.
The pavement management plan, which tackles collections of streets within neighborhoods for efficiency’s sake, is funded by about $3.45 annually. Some $2.5M comes from the town and nearly $1M from the state. The plan covers not just the roads, but also sidewalks and ramps in support of the town’s Complete Streets policy.
Note that some of the town’s main roads, like Pond Street and Rte. 135, could have funding provided through Natick’s capital plan rather than through the pavement management plan.
You can see in the slide shown here whether your street is up for some excitement this year or over the next couple of years. The roads shown in bold will need a little extra love because of their rough condition (Arbor and Oakridge are leftovers from last year).

Natick is hiring a company to take an inventory of its roads and their condition this year, and from there will flesh out the roads that need attention in 2027 and 2028. The initial thinking on the study is that it wouldn’t include unaccepted roads, but based on discussion during the presentation, that might be reconsidered.
As Westerling explained, the DPW treats roads differently based on their condition, with treatment scaling from less to more expensive. Some merely need crack sealing, while others need more aggressive milling and overlays. The worst roads require reclamation: “maximally intrusive work,” in Westerling’s words. Those are your bolded roads in the table above.
The town is looking to do crack sealing on 7 miles of roadway, milling and overlay on just over 3 miles, and reclamation on 0.6 miles (this will account for 44% of the overall cost). Town Administrator Jamie Errickson emphasized that the town gets more “bang for the buck” when it does proactive work, such as crack sealing, in a timely manner.
Special attention will be given as well to the intersection of Rte. 135 and Speen Street, which has been chewing up tires and vehicles and spitting them out. This work had been proposed by the DPW as part of the capital plan but also addresses an issue raised in a citizen petition for Spring Annual Town Meeting. It’s possible the proponent of Article 27 will recommend no action be taken if the town winds up addressing this intersection anyway.
The Select Board approved the pavement management plan.

[gview file=”https://www.natickreport.com/wp-content/uploads/2024/03/2024_Presentation.pdf”]

Heavily traveled Glen St is going to need a heck of a lot more than crack sealing. As both a driver and a biker, that road is taking its toll on me!
Great info on our roads. Thank you!
I swear Natick has some of the worst road conditions around.
Woodland Street between Union and Davis Brook is a mess. Dodging bumps, potholes and sewers is dangerous on this very narrow road with trees up to the edge of the pavement. People are forced into the middle of the road to avoid the obstacles and there’s going to be a head on crash!
Why us there a dog (Boston Terrier?) with an “N” on it on the slide in the corner?
Seem’s odd.
that’s your official town logo