The nonprofit seeking to put 32 affordable housing units on South Natick riverfront property housing a former school shared updates this past week before the Zoning Board of Appeals and Select Board. The Select Board voted 3-2 in March of 2023 to enter negotiations with Metro West Collaborative Development, which offered $100 for the town-owned property at 5 Auburn St. and said during the request for proposals process that it expects to get hundreds of thousands of dollars from the Natick Affordable Housing Trust to help bring the income-restricted housing to fruition.

You can find documents regarding 5 Auburn on the town website, and the developer also has a website promoting the proposed project, which would sit on a dead-end street off of Rte. 16 near the current location of the Natick Dam.
The nearly 2-hour ZBA meeting on Monday, Nov. 18 attracted more than 60 in-person attendees in addition to the Metro West team, including the executive director, a lawyer, and an architect, who between them gave a high-level overview of design plans and overall progress. The ZBA members asked a few questions (about parking, possible flooding), but were largely in listening mode. Chair David Jackowitz was patient in allowing both the developer and members of the public to have their say.
The consensus among neighbors in attendance—based on comments from longtime and newer residents who spoke and applause from others—was that they welcome affordable housing in the old school building. But they fear possible consequences of a denser project in an area of town that based on local government approvals and property development has undergone an extreme makeover in recent years with more big changes to come, including removal of the iconic dam. Meanwhile, the increasingly clogged Rte. 16 and the Pleasant/Eliot/Union St. intersection have remained the same structurally.
This makeover has been in the form of everything from several new schools to nearby multifamily housing and from a gas station-turned-used car lot to more seasonal events at Elm Bank Reservation. One cumulative effect of numerous one-off changes, from the lived experience of neighbors, has been increased traffic and a gridlocked main intersection, with regular hours-long mile backups on weekdays that make it tough to get in and out of side streets. A revamped riverfront park will be designed to attract more visitors to the area as well.
“I cannot tell you how much quality of life I have lost in the last 10 years,” said neighbor Dan Weddle, who expressed frustration during the ZBA meeting with increased traffic on Rte. 16 in recent years. He encouraged those doing traffic impact reports to consider this project within the context of numerous other developments in the area and not to overlook the impact that years of construction on this project will have.
Executive Director Caitlin Madden emphasized efforts by the team to devise a sustainable and affordable housing design that addresses feedback from town bodies and current residents, and that puts a focus on the historically significant former school building by positioning a new three-story structure behind it that faces the Charles River. Metro West refers to its repurposing of the school as “adaptive reuse.” The current front lawn facing Rte. 16’Eliot Street would remain open space.
(Madden shared a brief update at the Nov. 20 Select Board meeting, laying out a likely timeline for the project depending upon how requested funding pans out. She also was a guest on Nov. 25 at the Coffee with a Purpose group’s meeting, where she discussed the project.)
As is typical at such meetings, the ZBA hearing drew a crowd mostly from the neighborhood. A handful of affordable housing advocates also attended and spoke, with their focus on possible future residents and the great demand for affordable housing.
(Disclaimer: We live in this neighborhood. See the Natick Pegasus recording of the Nov. 18 ZBA meeting to draw your own conclusions from what transpired there.)
Latest on 5 Auburn St. plans
Metro West has been involved in various projects in Natick, but this would be its most involved. Madden pointed to past or ongoing projects in Hudson, Medway, and Newton to illustrate the outfit’s experience in the field, and cited meetings it has had for this project with neighbors, the general public, and town bodies.
Metro West earned a key state state eligibility approval in September and submitted its comprehensive application to the town after that. This is what the ZBA is now considering, and following this past Monday’s meeting, Metro West will go before the ZBA in the months to come on more specific matters, such as traffic, environmental, safety, and operations. Madden noted that Metro West has also received an approval that will give it access to federal historic tax credits for the proposed development; a similar state process is ongoing.
Metro West sees the project as “a once-in-a-generation opportunity to preserve a cherished community resource while providing the added benefit of affordable housing,” Madden stated. 32 units is seen by the developer as the number required to make the project economically feasible, the Metro West attorney said (one neighbor asked later whether Natick’s new Community Preservation Committee in years to come could subsidize a smaller Metro West project).

The plan is to offer rental units at 60% and 30% of area-median income (AMI) based on a state formula, and that would translate into monthly rents ranging from about $1,800 to $2,500 for those in the 60% bracket and less for those at the 30% AMI level. Apartments will be available in 1, 2, and 3 bedroom varieties, with nine planned for the old school, and 23 in the new building. The current school building’s gym would be converted into a community room, and be used for offices, etc. The new building would have horizontal clapboards and other design elements in keeping with neighborhood homes.
Overall, the project would have 45 vehicle parking spaces, plus 36 for bikes. Plans are for tree and shrub plantings as part of the screening and landscape design, and Metro West would introduce stormwater management, including via bio retention areas, that the site currently lacks. A dark sky compliant plan is designed to shield neighbors from the multi-tenant project’s lighting.
Funding milestones include plans to submit an application to the Metro West Home Consortium next month, and the big one, an application to the state’s Executive Office of Housing & Livable Communities (EOHLC). Madden described the EOHLC funding process as “extremely competitive” and said her team will need to show significant progress in the zoning process by the February funding deadline.
If that doesn’t pan out, Metro West can take a shot at what she described during her Select Board briefing as the state’s “highly selective mid-year mini-round.” If approval isn’t granted then, Metro West would look toward a winter funding round. “It’s not often that projects are funded in their first applications to the state,” Madden told the Select Board. The next best case, she said, would be to score funding in the mini-round, start construction at the end of 2026 and finish it in 2028.
Questions have arisen about whether the incoming federal administration could have any impact on available housing dollars, as the great majority of Metro West’s projected funds would stem from federal sources. Madden has expressed optimism about funds based on historic bipartisan support.
Affordable housing advocates in the audience boosted the case for this project at this location.
Ganesh Ramachandran, chair of the Natick Affordable Housing Trust Fund Board, said that while some see the project being on a dead end, you can also view it as being on a state highway, in Rte. 16. He described it as a walkable neighborhood near a library and retail (this includes an art/framing gallery, realtor, pizza shop, and coffee shop). What’s more, he cited stats showing the challenges of affording a home in Natick. “To have a development that can cater to people making up to 30% of AMI or 60% of AMI, it’s extraordinary, and I think it’s something we should celebrate rather than oppose,” he said.
Neighborhood feedback
Project abutter Mark Budgen kicked off the neighbor comments with an extended presentation, including a visual about a school-turned-15-unit-housing development in New Bedford. He raised concerns about a project that would balloon population on the street from about a dozen to more than 100.
“We always welcomed some kind of housing here. Affordable fine. That was always on the table,” he said. “What I find challenging is the scope of the project. We have a sleepy little dead end street with four houses, less than 500 feet… I’ve done some research on dead-end streets and housing. You would never have a project this size at the end of a dead-end street. There’s one way in and one way out…” Like others, he raised safety issues based on emergency vehicle access.
“There’s such a thing as too much of a good thing,” Budgen said. “We need affordable housing. This is a great site for affordable housing. But let’s take a reasonable approach and make it a win-win for everybody.”
Neighbors expressed skepticism regarding the initial traffic study, based on in-person sampling of traffic and queuing, expert evaluation, and using industry standards (this study will be peer reviewed by a town-approved consultant). The study makes no mention of the likely influx of delivery vehicle traffic, only referring to such vehicles in terms of their ability to navigate Auburn Street and the development. The report devotes just two paragraphs to public transportation, as there is no regular service within a mile—the closest is at the MetroWest Medical Center, which is more than a mile up Union Street. This report is not unlike most we’ve seen for local projects in that its scope is mainly on the project itself and makes limited mention of the effect of other area projects (it does cite the independent senior living complex going up on Union Street). Though it does include recommendations for traffic mitigation at the Union/Pleasant/Eliot intersection.

Neighbor Stephanie Smith said “I fail to understand why the town would choose to proceed in a relatively antiquated approach to an affordable housing project. One where we create an urban environment in the middle of a suburban community by cramming as many units as possible and creating an adversarial relationship with the existing neighbors.”
Smith encouraged Metro West to work with neighbors. “The choice is to build a fortress or create friends, be a nemesis or create neighbors, wreak havoc on a community or be willing to do something really wonderful. I implore you not to do this just because you can. Do the right thing for this neighborhood and the town because you should.”
Natick is currently 5 units under the state threshold for affordable housing (10% of overall housing stock), according to the town, though the affordable units that public transportation-friendly projects closer to Natick Center will soon contribute should put the town over that threshold. The units proposed at 5 Auburn St., would all count toward the town’s subsidized housing inventory as well down the road (Note that the 10% threshold is something of a moving target as population increases or decreases according to census counts.)
ZBA Board Chair Jackowitz gave neighbors some comfort by acknowledging, after hearing their comments, that “these concerns are real and they will be addressed in some form or fashion during this process. I don’t know what spits out the other end, but these comments are invaluable to the decision making process and this is how it works.”
Keep an eye out for coming meetings, from ZBA (Dec. 9 in-person meeting will focus on traffic reviews and waiver requests) to Select Board to Conservation Commission, that will include agenda items on the 5 Auburn St., project and provide opportunities for public comment. Natick Report runs a weekly sampling of upcoming meetings and highlights items of public interest.