Brief updates on the South Natick Dam (spillway) removal and related riverside parks improvement project were shared at the June 26 meeting of the Natick Conservation Commission (see recording, about 32 minutes in).
Environmental Planner/Conservation Agent Claire Rundelli said the Natick Recreation and Parks Department has submitted a letter of interest to the Community Preservation Committee related to the next year of work on improving the riverside parks adjacent to current dam site. The Community Preservation Committee, which has been stockpiling revenue from a property tax surcharge, has started the process of accepting its first-ever applications to use that money.
The town’s goal is to sync up spillway (waterfall) removal with park improvements.
“We’re going to be focusing the next year on permitting the parks projects. The dollar value that goes along with that is not a dollar value that is competitive at a grant level,” said Rundelli, adding that the town decided not to apply for state Municipal Vulnerability Program (MVP) funding for this aspect of the project.
About $100k is being requested of the CPC, which had collected about $2.5M as of May. Park and Recs would use funding for permitting and final construction documents and bid specs.
As for the dam and spillway (we get asked more about this than anything here at Natick Report), plans are for removal to happen next summer.

The Select Board voted in late 2022 to remove the iconic dam structures to save money, avoid liability in case of a breach, and restore the river to a more ordinary state.
Rundelli said during the Conservation meeting that the town is in discussion with the U.S. Army Corps of Engineers about whether the dam removal will impact the Charles River Natural Valley Storage Area, which is used for flood control. The Army Corps of Engineers has “conflicting records” on the relationship between the dam and storage area. It’s possible Natick will need to file an additional application for a Section 408 finding related to this, but Rundelli said it’s not expected this would affect any bid timelines for construction work on the spillway removal.
Bids are expected to go out around the start of 2026, and the town awaits word on possible state and other funding.