Natick has made great progress on Charles River dam/spillway removal permitting and park renovation design, but still has plenty of work to do on the funding front—especially in light of some federal programs being nixed.
The Select Board this Wednesday is set to get updates on both projects.
The dam/spillway removal is further along based on a memo from the town’s Department of Public Works to the Select Board.
Though at least one potentially significant funding source for dam removal has dried up as much as the river itself in South Natick.
View this post on Instagram
The federal government has killed the Building Resilient Infrastructure and Communities (BRIC) Program, which Natick had already applied for in March, seeking $612,500.
A separate FEMA Hazard Mitigation Grant Program application for $612,500 (assumes a state funding match) is under review.
Better news for the team working on this project is that it is hopeful to receive notice from the Dam and Seawall Construction Grant Program regarding its application for a $1m grant by the end of August.
Spillway removal is projected to happen next summer, allowing the river to run free.
The total cost of the project is estimated by a town consultancy at $1.2M. Fixing the dam/spillway was estimated to cost well over $2M.
The town has made it through seven of 8 major permits/regulatory reviews, and expects to wrap up the last one this fall.
The Select Board voted in 2022 to remove the spillway, largely for financial and environment reasons.
Under a sort of parallel project to improve the parks around the river near the current dam and spillway, the town recently received permit-level designs and cost estimates from a consultancy for the rehabilitation of the parks, according to a memo to the Board from the Community Services Department. Designs under consideration are more modest than concepts aired early in the process, and more serious waterfront changes will be explored after review of how the river behaves post-spillway removal.
Estimates for construction range from $1.735m to $1.815m. Where funding will come from remains to be seen, but the town is seeking $82,500 in Community Preservation Act funding this fall to support finalized design work and permitting.
“Looking ahead, staff continue to monitor opportunities to fund construction. A combination of state grants, CPA funding and capital will all be further explored in FY26,” per the Community Services Department memo.

Funding the park design seems like exactly the sort of project that made me vote for the CPA in the first place. The new park would
be valued by the people who have loved the dam and regret the necessity of its removal.