• Sign up for free email newsletter
  • Advertise
  • Events calendar
  • Donate to support our work
  • About us (contact us)
 
 

Natick Report

Since 2020: More than you really want to know about Natick, Mass.

  • Restaurants, sponsored by Tama Sushi & Hibachi
  • Camps, sponsored by NEOC
  • Private Schools—sponsored by Fay School
  • Public schools, sponsored by Sexton
  • Preschools, sponsored by Longfellow, Wellesley
  • Letters to the editor
  • Guidelines for letters
  • Sports schedule & results
  • Embracing diversity
  • Charities/Community
  • Arts
  • Kids
  • Business
  • Environment
  • Top 10 things to do
  • History
  • Seniors
  • Deaths
  • Government meetings
  • Natick Center Cultural District—restaurants, shops, services

Top Stories

 
  • —Top 10 taxpayers
  •   —Anyone's Game readies to open in '27'
  • —What's open at Thanksgiving time
 
 

Advertisements

 
 

Where will South Natick fire station wind up?

October 25, 2026 by Bob Brown

oct 17 south natick fire station
South Natick fire station

A consultant hired to examine the South Natick fire station’s condition found that the building is in generally good shape, but that it does need major renovations and the town may be better off relocating it to a larger space to meet new safety standards and emerging needs.

The current building is 2,675 sq. ft. but a space needs analysis showed that a building almost three times as big could be required. Current staffing is three firefighters per shift, for a total of 12 staff, but the standard is for four firefighters per engine company, according to the study.

The current undersized site next to the Union Street/Rte. 16 intersection could work, according to a study slated to be discussed at the Select Board meeting on Oct. 28. But other spaces being recommended for further research include the multi-purpose court on Pleasant Street near the former spillway, the gas station/car sales lot at 9-11 Eliot St., and the Memorial Elementary School lot.

“Considering the space needs, reuse of the current station and site will be difficult—but not impossible,” the study states.

Possible alternatives to the current 2 Robert Sproule Lane address are all intriguing given the town’s stated intention to redevelop the multi-purpose court as part of its renovation plans related to the spillway removal, its efforts to renovate or rebuild Memorial school, and the fact that it doesn’t own the gas station property. The study acknowledges that all four sites that warrant further examination, including the current one, have their pros and cons.

“After reviewing the collected data and building test fits, we recommend the Town move to conduct a detailed feasibility study for expansion on the current site and/or relocation of Station 2 to a new site,” the study states. (It’s common for one consulting project like this to lead to a bigger dollar follow-on for that same firm.)

Site recommendations were based on a handful of criteria, including response time, vehicle ingress/egress, and neighborhood impact. It’s possible that a relocation could improve response time, the study concludes.

(Update 10/28/26): Despite the fact that the multi-purpose court was identified in the report as one of four viable sites based on site selection criteria, Town Administrator Jamie Errickson said during the third night of Fall Annual Town Meeting that the multi-purpose court area is actually not a viable spot for a fire station “for many, many reasons.”)

A change of location for the fire station would be another part of South Natick’s extreme makeover, including the recent spillway removal, plans for riverside park improvements, and plans for a deeply affordable housing complex at 5 Auburn St. sort of across Rte. 16 from Station 2. A couple of new school buildings have also opened in the area over the past decade.

Moving the relatively small fire station to another South Natick location legitimately wouldn’t increase traffic much, if at all, wherever it is situated. However, the other boot to drop if the firehouse gets relocated would be what becomes of the current space—would the town use it or sell it for something that would pile onto Rte. 16’s already jammed traffic situation? Neighbors might want to stay on top of this.

fire station test fit map
Test fit locations in Station 2 study

Natick has four fire stations, including headquarters in Natick Center as part of the public safety facility that includes the police station, the West Natick station that opened in 2021, and the small East Natick station on Rhode Island Avenue near Oak Street and Rte. 9.

Fire station upgrades have become increasingly challenging given new national standards intended in large part to keep firefighters safer (decontamination areas to help address high rates of cancer, for example), to accomodate larger vehicles and storage, and to provide separate accommodations based on gender.

Next door, Wellesley is seeing this play out and it’s creating lots of angst amongst neighbors of a possible new station as well as those who use the community gardens and nature trails at the town-owned North 40 property recommended by a consultant and the fire department for further study.

Context Architecture, the same firm that conducted Natick’s $50k Station 2 study, has done a fire station master plan study for Wellesley looking at future fire station needs. This study has identified possible sites—including two on busy, narrow Weston Road—for a new headquarters location to address shortcomings at the current headquarters on Rte. 9 west and the charming Wellesley Square location that is about 100 years old and way too small (the recommendation from the report is to keep the Rte. 9 station, but it would become a substation to a new headquarters building). The Wellesley Select Board has been undertaking a public feedback process and is soon expected to make a recommendation to fund a feasibility study at Annual Town Meeting in the spring. The Wellesley fire station master plan estimates future construction costs at approximately $65–$73 million.

Natick is looking at a much smaller substation facility in South Natick, with early total cost estimates ranging from about $14m to $20m based on scope and location. Better cost estimates would come after a feasibility study is conducted. Under the cost evaluation section of the study, there’s an indication of 2028 being a possible start for construction.


 

If you’re fired up about having a dedicated local news source in Natick Report, please consider making a tax-deductible donation. Contributions less than $14m to $20m are welcome.

Print Friendly, PDF & Email

Filed Under: Fire, Government

Comments

  1. Joe says

    October 27, 2026 at 6:03 pm

    I’m sorry but is the town living in thd stone age?that firehouse is ANCIENT and looks more like someone’s house as opposed to a fire station.How is it we can have s brand new beautiful firestatuon on rte.9 and at the same time have one thatblioks like it belongs to an elderly couple in 1920’s Georgia?

    • Richard Hertz says

      October 28, 2026 at 1:10 pm

      I’m very sorry, but this is far too nice for Georgia.

  2. Sr. Wences says

    October 27, 2026 at 9:04 pm

    Excellent coverage of the options and the related history from Wellesley.

    Thanks.

  3. Cote says

    October 28, 2026 at 8:01 am

    Why do we always rebuild, but we can’t retrofit? Homeowners usually don’t tear down their entire house when they want to improve or increase the size. Even business retrofit before they teardown when improving and increasing size. Yet government and municipalities always clean slate the whole thing. But yes, expanded national gir code. When was the last fire in Natick? I am all for public safety, but the fires historically are down to improved fire code and building materials, but we keep putting money into their engines at older historical data. It seems the fires that do occur are much bigger and go to other surroundings towns anyhow. So maybe this firehouse really needs to revamped to a EMT satellite location and have the fire engines dispatched from downtown or surrounding towns. I bet we could even pay those towns for the dispatch and it would still be cheaper (fires only) than 16 million and another override.

  4. Robert Taylor says

    October 28, 2026 at 1:22 pm

    Natick is NOT Wellesley . I wish people would stop comparing other town to Natick. We have our own wants and needs which must align with budget/income.

  5. Sandy says

    October 28, 2026 at 4:14 pm

    I sincerely hope they don’t use the skatepark site. I’m really looking forward to a gorgeous park on the Charles River in the coming years.

    • Bob Brown says

      October 28, 2026 at 7:11 pm

      An update: Town Administrator Jamie Errickson said during the third session of Town Meeting on Oct. 27 that this site is actually not viable for a fire station…I’ve added a note about this to our original post. Thanks for your comment, Bob

    • Lucy says

      October 30, 2026 at 7:39 pm

      I absolutely agree! The town has already said that that old skate park area is to be part of the continuation of park space as they help preserve this area adjacent to the old spillway. Hopefully something attractive and not all paved over!…enough building and construction !

 
 
Natick Art Association, Holiday Gift Fair

Tip us off!

Please send news tips, photos, ideas to natickreport@gmail.com

Please support your local news source with a tax-deductible donation by scanning the QR code or by clicking on it.

natick report QR code

Advertisements

Categories

  • Animals
  • Art
  • Bacon Free Library
  • Beyond Natick
  • Books
  • Boston Marathon
  • Business
  • Camps
  • Careers
  • Charity/Fundraising
  • Community
  • Construction
  • COVID-19
  • Education
  • Election
  • Embracing diversity
  • Employment/careers
  • Entertainment
  • Environment
  • Fashion
  • Fire
  • Food
  • Gardens
  • Government
  • Health
  • History
  • Holidays
  • Housing
  • Humor
  • Kids
  • Legal
  • Letters to the editor
  • Media
  • Military
  • Morse Institute Library
  • Music
  • Natick Election 2022
  • Natick Historical Society
  • Natick History Museum
  • Natick Mall
  • Natick Nest
  • Natick track
  • Neighbors
  • Obituaries & remembrances
  • Older adults
  • Opinion
  • Outdoors
  • Override
  • Parents
  • Police & crime
  • Real estate
  • Recycling Center
  • Religion
  • Residential property sales
  • Restaurants
  • Schools
  • Shopping
  • South Natick Dam
  • Sports
  • Technology
  • Theater
  • Town election 2021
  • Town Election 2023
  • Town election 2024
  • Town election 2025
  • Town Election 2026
  • Town government meetings
  • Town Meeting
  • Transportation
  • Travel
  • Uncategorized
  • Vacation
  • Veterans
  • Volunteering
  • Voting
  • Weather
lion publishers
  • Bluesky
  • Facebook
  • Instagram
  • Twitter

Sign up now for free email newsletter & stay in the Natick loop

* indicates required
Our newsletter is free, though we gladly accept contributions to support our work.

Most Read Posts

  • What's open and closed at Thanksgiving time in Natick, 2026
  • Fire Pit Hosts welcomed to Cochituate Rail Trail for New Year's Eve
  • After much discussion, Natick retains a single tax rate
  • Learn about getting involved in Natick town government
  • Fueled by 4 Oliveira touchdowns, Natick beats Framingham 42-20 in Thanksgiving Day football game

Click image to read The Swellesley Report

The Swellesley Report

Upcoming Events

Nov 28
All day

Natick Center’s Holiday Stroll

Nov 29
2:30 pm - 5:00 pm

Natick Holiday Lighting and Santa Parade

Dec 1
7:00 pm - 8:00 pm

Learn about getting involved in Natick government

Dec 4
7:30 pm - 9:30 pm

Natick High School Theatre Fall Musical—”Dear Evan Hansen”

Dec 5
2:00 pm - 4:00 pm

Natick High School Theatre presents, “Dear Evan Hansen”

View Calendar

Privacy policy

© 2026 Natick Report
Site by Tech-Tamer · Login